The county council has voted 40 to 8 to apply for powers to build the Waterbeach busway. Stops at Butt Lane, Landbeach and a 1,600-space hub; buses by 2031.

Cambridgeshire County Council will apply next month for the powers to build a busway from Waterbeach New Town to north Cambridge. Full Council backed the application on Tuesday 13 October by 40 votes to 8, with 7 abstentions.

The 6.5km route runs through Impington, Milton and Landbeach. It would carry buses on a dedicated track across farmland, with a new 1,600-space travel hub opposite the new town.

The vote is not planning permission. The council is asking the Transport Secretary for a Transport and Works Act Order, which would also give it compulsory purchase powers over the land. The council’s report expects a public inquiry in mid 2027 and buses running in mid to late 2031.

Where the busway would run

The report describes the route from south to north:

  • Start: a junction with the existing Cambridgeshire Guided Busway, just west of where it passes under the A14.
  • Milton Road and Butt Lane, Impington: the busway runs north across fields to a signalised T-junction on Milton Road/Butt Lane, with a bus stop. Buses then run on the road east towards Milton Park and Ride. The report says Butt Lane “will be significantly improved and widened” for them.
  • Milton Park and Ride: the entrance is modified so buses can call at the site and leave again onto Butt Lane. The guided track restarts just west of the Park and Ride junction.
  • Landbeach Road: a signalised crossroads just south of Landbeach village, with a bus stop.
  • Waterbeach Road: the track passes Landbeach to the east, then crosses Waterbeach Road at another signalised crossroads. There is a stop here, with drop-off space.
  • The travel hub: up to 1,600 vehicles, west of the A10 and opposite Waterbeach New Town. It links to a new roundabout on the A10, which will also be the new town’s southern entrance. From there, buses join the roads through the new town towards the planned new railway station.

A maintenance track runs beside the guided sections. It doubles as a path for walking and cycling.

Diagram of the proposed Waterbeach to Cambridge busway from south to north: a junction with the Cambridgeshire Guided Busway west of the A14 underpass; a stop at Milton Road and Butt Lane, Impington; Milton Park and Ride; a stop at Landbeach Road south of Landbeach; a stop with drop-off at Waterbeach Road; and a 1,600-space travel hub west of the A10 opposite Waterbeach New Town. Timeline: application November 2026, public inquiry mid 2027, statutory approval mid 2028, construction from late 2029, opening mid to late 2031.
The route and timetable as set out in the county council's report to Full Council, 13 October 2026. Graphic by South Cambs Online.
Share this chartFacebookWhatsAppX

What has changed since the first vote

The council first agreed to apply in February 2025. That application was never made, and the report sets out why:

  • The Environment Agency revised its flood maps in March 2025. That forced a major redesign of flood compensation and drainage.
  • Groundwater readings over winter 2026 were “much higher than anticipated”. Ponds and water storage at the travel hub and along the route had to be redesigned.
  • The A10 roundabout is being designed by Urban & Civic, the new town’s developer. It was expected to get planning permission in autumn 2025, but did not until June 2026.

Legal advisers told the council that a gap of about six months between the vote and the application would be normal. The gap had reached 21 months. A fresh vote also means the council no longer needs a confirming vote after the application goes in, under rules that changed in February 2026.

The scheme has also changed in places. Among the changes the report lists:

  • a strip of extra land, 3m wide, along the western edge of the route for landscaping and fencing
  • more land around the travel hub for an embankment and a path to a bridge over the A10
  • the diversion of the recently built Mere Way bridge link
  • less land taken south of Butt Lane, to reduce the effect on public open space
  • the maintenance track moved to the bottom of the busway embankment, further from the buses
  • a pond north of Butt Lane and further ponds at the travel hub

Land, and the open space at Milton

The application will include powers to buy land compulsorily. The report says talks with landowners are going on, and the council hopes to buy most of it by agreement. Agents advising the council estimate the land will cost no more than £3.5 million.

One piece of land needs special handling. Landscaping and a buffer zone north of the Milton recycling site “appears to be used on an informal basis as open space”. The law protects land used that way. The council has found replacement land north of Butt Lane and will ask the housing secretary to certify the swap.

How councillors voted

A resolution of this kind must win a majority of the whole council, not just of those present. With 61 councillors, that meant at least 31 votes. The recorded vote gave it 40.

Group For Against Abstained
Liberal Democrat and Independent 30 0 0
Labour 5 0 0
Conservative 3 6 0
Reform UK 2 0 6
Green 0 2 0
Non-aligned Independent 0 0 1

The county councillors for the divisions along the route all voted for it: Anna Bradnam (Waterbeach), Ros Hathorn (Histon and Impington) and Yasmin Deter (Cottenham and Willingham).

When it would happen

The report gives this timetable, assuming objections lead to a public inquiry:

  • November 2026: application submitted to the Department for Transport
  • Mid 2027: public inquiry
  • Mid 2028: statutory approval (another part of the report says the order could come into force in early 2028)
  • Mid 2029: detailed design finished and a target cost agreed
  • Late 2029: full business case approved and construction starts
  • Mid to late 2031: buses running

Building it is not yet guaranteed. The council’s finance director warned that the scheme may need “interim financing arrangements” before developer contributions arrive. A final decision to build will depend on funding being “robust” at that point. Because of local government reorganisation, that decision may fall to a new unitary council.

The benefit to cost ratio is 1.4, based on conventional transport economics alone, the report says.

What it means for you

  • You can comment once the application goes in. Objections and other representations go to the Transport Secretary during a set period after submission, under the Transport and Works Act process. The report says owners and occupiers of land being bought who object are entitled to a public inquiry or hearing. We will publish the deadline when the application is lodged.
  • Butt Lane will change. Buses would run along it between the guided sections, and it would be widened. Expect construction disruption from late 2029 at the earliest.
  • Landbeach gets two nearby stops. They sit at the new signalised crossroads on Landbeach Road and Waterbeach Road. The parking is at the travel hub by the A10.
  • Rail users: the busway is meant to feed the new Waterbeach station planned for the new town. The decision on closing the existing station is separate, and rests with the Department for Transport. Usage of the current station is at a five-year high.

The Cambourne to Cambridge busway went through the same process and was approved in September, after a 22-day inquiry. The Greater Cambridge Partnership’s scheme page carries the earlier consultation material.