The A14 eastbound now shuts at Milton only on 2, 3 and 4 November, 8pm to 5am. River Cam bridge repairs are paused again until early January 2027.

Updated 1 November: National Highways paused the bridge repairs again on 29 October. Only three nights of closures remain this month, and they are for separate technology work. This story has been rewritten to match.

The A14 eastbound between Milton and Fen Ditton will now close on just three nights this month: Monday 2, Tuesday 3 and Wednesday 4 November, 8pm to 5am. The 21 nights of closures announced on 23 October have been cut back, because repairs to the fire-damaged River Cam bridge near Horningsea are on hold again.

National Highways posted the change on 29 October, headed “Change to work programme”, on its River Cam bridge scheme page. It says: “We’ve paused our planned bridge work due to technical challenges with the bridge design.” It now expects to “continue work from early January 2027”.

The three nights left are for roadside technology work on the eastbound side between junction 33 (Milton) and junction 34 (Fen Ditton), which National Highways says “will continue as planned”.

The diversion for the three nights

The signed diversion is the long one:

  • leave the A14 at junction 31 (Girton)
  • take the M11 southbound
  • join the A505 eastbound, past Duxford and the Abingtons
  • take the A11 northbound
  • rejoin the A14 eastbound at junction 36

The scheme page does not say how drivers joining the A14 at Histon or Milton should go, so follow the signs on the night. The A10 and A142 diversion that was planned for 11 to 22 November is no longer needed.

A14 eastbound, Milton junction 33 to Fen Ditton junction 34. Booked on 23 October: 21 nights, 2 to 22 November. Now: 3 nights, Monday 2 to Wednesday 4 November, 8pm to 5am, for technology work, diverted via junction 31 Girton, the M11 southbound, the A505 eastbound and the A11 northbound to rejoin at junction 36. Bridge repairs paused until early January 2027.
What changed between National Highways' 23 and 29 October updates. Graphic by South Cambs Online.
Share this chartFacebookWhatsAppX

Why the bridge is being repaired

National Highways describes the scheme as “essential maintenance on the River Cam Bridge near Horningsea in Cambridgeshire, due to fire damage”. It is also upgrading safety features, resurfacing the road and renewing roadside technology between junctions 33 and 34. The scheme page gives:

  • a cost of £4 million
  • a start date of 6 October 2025
  • an end date of January 2027

National Highways’ 28 August update said the 40mph limit would stay “throughout our work”. The 29 October update does not say whether it stays during the pause.

What happened to the autumn closures

This is the third timetable since the summer, and the second pause.

  • 28 August: National Highways advertised a westbound full closure between junctions 34 and 33 on weeknights from 10 September to 6 November, then 14 eastbound shifts from 9 to 26 November.
  • 24 September: the bridge work was paused “due to technical challenges with the bridge design”, with work expected “from early October 2026”. Its weekly closure reports, which we check for our roadworks page, carried just one westbound bridge night, booked for 28 September.
  • 23 October: an update headed “Work restarts” booked the eastbound carriageway shut every night from 2 to 22 November, with a westbound phase two from January 2027.
  • 29 October: the bridge work was paused again, with the same wording, leaving only the 2 to 4 November technology nights.

The scheme page still gives January 2027 as the end date. It has not said what the January restart means for the westbound phase two.

What it means for you

  • If you drive east on the A14 late at night, from Huntingdon, Bar Hill or Girton towards Newmarket, plan for a diversion on Monday 2, Tuesday 3 and Wednesday 4 November, 8pm to 5am.
  • The rest of November is clear of bridge closures. If you had planned around the 11 to 22 November nights, you no longer need to.
  • Duxford, Pampisford and the Abingtons sit on the diversion via the A505 and the A11 for those three nights.
  • Milton, Landbeach and Waterbeach will not now get the extra overnight A10 traffic that the second November run would have sent their way.
  • Expect the bridge closures to come back in January. National Highways has not published dates yet.
  • Closures can change at short notice. National Highways says so on the scheme page. Our South Cambs roadworks page is rechecked against the weekly closure report on every visit.